Commercial Scale
Some Specifics:
​
-
Location: Maitland, Ontario​
​
-
Demonstration Facility Size: 5,000 ft3
​
-
Processing Capacity: 10,000 Litres per Day
​
-
Conversion Chamber Size: 4’H x 4’W x 8’L
​
​
Major Milestones:
​
-
Completed Startup Trials: December 2021
​
-
1st 24-Hour Run: February 2022
​
-
1st Multi-Day Endurance Run: April 2022
​​
-
1st Commercial Customer: March 2023

Ongoing Accomplishments:
​
Time of Operations: 1,500+​ hours
​
Liquids Processed: 230,000+ litres (60,000+ gallons)
​
Syngas Produced: 225,000+ cubic meters (8,000,000+ cubic feet)​
​
Data from Operations: 124,000,000+ records
​